The job analysis report is a weekly generated
report developed from field input showing percent complete of work items as
well as productivity of craft labor with respect to budgeted (estimated) man
hour allowances per activity and an accumulative total for all job
activities/codes.
- The assigned Project
Engineer will develop the job analysis input information, (i.e. activities,
quantities, allocated man hours, etc.) from the coded information used to
breakdown the original estimate for scheduling input. The job analysis
activities will mirror those activities of the overall project schedule and
monitor each activities percent complete, man hour expenditures, productivity
factors and total job progress and work factors. The job analysis report will
be updated weekly by the on-site Project Engineer via field input from each
craft discipline Foreman. The weekly updated job analysis information will
provide the basis for scheduling/progress update and percent complete
determination.
|