Owner: Bayer Corporation

Contract Holder: Gilbane Process

Scope of Work: Clinical Manufacturing Facility - Instrumentation Installation

Installation of Glycol system consisting of fabrication of clean room skids, power, and lighting. Procurement and installation of PLC cabinets, software configuration and testing. Furnishing and installation of field instrumentation and all required process tubing and supports. Performed calibration, loop check, and start-up.

Type of Contract: Lump Sum

Contract Period: February 2, 1999 - May 16, 1999

Contract Manhours: 2,600

Contract Value: $672,000

Owner: Pfizer, Inc.

Contract Holder: Gilbane Building Co.

Scope of Work: Pfizer Inhalable Insulin Facility

Furnishing and installation of power and controls wiring, conduit, conduit supports, cable tray, lighting, and switchgear. Also included is the furnishing and installation of field instruments, process tubing, air supply, sub header pipe, calibration, loop check, start up and commissioning.

Type of Contract: Lump Sum

Contract Period: July 31, 2000 - June 22, 2001

Contract Manhours: 24,000

Contract Value: $3,014,000

Owner: Siemens Westinghouse Power Corp.

Contract Holder: SM Electric Company

Scope of Work: AES Ironwood Co-Generation Project

Mechanical instrumentation work including the installation of all BOP instruments, heat traced instrument enclosures. Responsible for the furnishing and installation of all process tubing, sample tubing, tubing supports, raceway, socket weld fittings, air supply from air header taps, calibration of field BOP instruments, all skid mounted instruments and loop check.

Type of Contract: Lump Sum Converted to Time & Material

Contract Period: August 1, 2000 - May 31, 2001

Contract Manhours: 16,000

Contract Value: $1,450,000