Owner: PEMEX
Contract Holder: Gulf
Marine Fabricators
Scope of Work: "PEMEX
15,000 Ton Production Deck Facility
Complete power,
electrical, controls, lighting, instrumentation, communications, fire &
gas, ESSI, ESD, and nav-aid system installation, integration, testing, and
pre-commissioning. The complete electrical and instrumentation systems were
installed and hardwired via a plasti-bond conduit system and single conductor
wiring in lieu of the more traditional cable tray and CLX type wiring and
required a tremendous effort in craft training and special tooling for the
conduit system.
Type of Contract: Unit
Rates / Lump Sum
Contract Period: May
2000 - March 2001
Contract Manhours:
138,000
Contract Value:
$6,600,000 |
|
Owner: Mobile Producing
U.S.A.
Contract Holder: Gulf
Marine Fabricators
Scope of Work: Mobile
Jade Production / Drilling Facility
Furnish, install,
test, pre-commission and start-up complete power, control &
instrumentation, fire & gas, communication, navigation and marine systems
for 9500 ton drilling & production deck facility.
Type of Contract: Lump
Sum / Unit Rate Conversion
Contract Period:
February 1999 - August 1999
Contract Manhours:
112,000
Contract Value:
$5,128,000 |
|
Owner: PEMEX
Contract Holder: Gulf
Marine Fabricators
Scope of Work: PEMEX
7,500 Ton Booster Deck
Complete power,
electrical, controls, lighting, instrumentation, communications, fire &
gas, ESSI, ESD, and nav-aid system installation, integration, testing, and
pre-commissioning. The complete electrical and instrumentation systems were
installed and hardwired via a plasti-bond conduit system and single conductor
wiring in lieu of the more traditional cable tray and CLX type wiring and
required a tremendous effort in craft training and special tooling for the
conduit system.
Type of Contract: Unit
Rate / Lump Sum
Contract Period: May
2000 - March 2001
Contract Manhours:
72,000
Contract Value:
$3,800,000 |
|
Owner: PEMEX
Contract Holder: Gulf
Marine Fabricators
Scope of Work: PEMEX
8,000 Ton Booster Deck
Complete power,
electrical, controls, lighting, instrumentation, communications, fire &
gas, ESSI, ESD, and nav-aid system installation, integration, testing, and
pre-commissioning. The complete electrical and instrumentation systems were
installed and hardwired via a plasti-bond conduit system and single conductor
wiring in lieu of the more traditional cable tray and CLX type wiring and
required a tremendous effort in craft training and special tooling for the
conduit system.
Type of Contract: Unit
Rate / Lump Sum
Contract Period: May
2000 - March 2001
Contract Manhours:
68,000
Contract Value:
$3,400,000 |
|
Owner: Transocean
Contract Holder: Gulf
Marine Fabricators
Scope of Work: Deep
Seas Spirit DES Module
Complete systems
installations, integration, testing, and pre-commissioning for electrical,
power, controls, instrumentation, fire & gas communications, navigational,
and drilling systems for 11,400 tons of process module fabrication for the 850'
Deep Seas Spirit Drill Ship. The Deep Seas Spirit has a 400' fully automated
drill Derrick capable of drilling in 12,000' of water and up to depths of
45,000'.
Type of Contract: Lump
Sum
Contract Period: June
1999 - March 2000
Contract Manhours:
86,000
Contract Value:
$3,200,000 |
|
Owner: Transocean
Contract Holder: Gulf
Marine Fabricators
Scope of Work: Deep
Seas Discovery
Complete systems
installations, integration, testing and pre-commissioning for electrical,
power, controls, instrumentation, fire & gas communications, navigational
and drilling systems for 11,400 tons of process module fabrication for the 850'
Discovery Drill Ship. The ship has a 400' fully automated drill Derrick capable
of drilling in 15,000' of water and up to depths of 35,000'.
Type of Contract: Lump
Sum
Contract Period: July
1999 - January 2000
Contract Manhours:
86,000
Contract Value:
$3,200,000 |
|
Owner: Gulf Marine
Fabricators
Contract Holder: Gulf
Marine Fabricators
Scope of Work: Aker
Gulf Marine - New Piping Manufacturing Facility
Complete power,
electrical, controls, lighting, instrumentation and communication hook-up for a
new construction of the AGM Pipe Fabrication Building. Roll mill, rotor blast
and paint shop.
Type of Contract: Time
& Material
Contract Period: May
1998 - October 1998
Contract Manhours:
64,250
Contract Value:
$1,985,000 |
|
Owner: Elf Exploration,
Inc.
Contract Holder: Gulf
Marine Fabricators
Scope of Work: Elf
Virgo Production Facility
Furnish, install,
pre-commission & start-up of complete power controls, instrumentation, fire
& gas, communications, navigational and marine systems for 6,800 ton
drilling & production facility.
Type of Contract: Lump
Sum
Contract Period:
November 1998 - June 1999
Contract Manhours:
54,000
Contract Value:
$2,161,000 |
|
Owner: Mobile Producing
U.S.A
Contract Holder: Gulf
Marine Fabricators
Scope of Work: Mobil
Jade Offshore Hook-Up
Complete offshore
hook-up, start-up assistance, and commissioning of Mobil Jade platform on site
offshore Gulf of Mexico.
Type of Contract: Time
& Material
Contract Period:
December 1999 - March 2000
Contract Manhours:
28,000
Contract Value:
$1,500,000 |
|
Owner: Anadarko
Petroleum Corporation
Contract Holder: Gulf
Island Fabrication
Scope of Work: Anadarko
Hickory Production Deck
Complete power,
electrical, controls, lighting, instrumentation, communications, fire &
gas, ESSI, pre-commissioning, check-out, and start-up of a 4,000 ton production
deck.
Type of Contract: Lump
Sum
Contract Period: April
2000 - July 2000
Contract Manhours:
29,300
Contract Value:
$1,311,000 |
|
Owner: Transocean
Contract Holder: Gulf
Marine Fabricators
Scope of Work: Deep
Seas Spirit Integrated Work
Complete electrical
and instrumentation hook-up on the 1st of two (2) drilling ships.
Type of Contract: Lump
Sum
Contract Period: June
1999 - March 2000
Contract Manhours:
27,500
Contract Value:
$934,000 |
|
Owner: Amerada Hess
Corporation
Contract Holder: Gulf
Marine Fabricators
Scope of Work: Bald
Pate Project - Garden Banks 260A
Complete power,
electrical, controls, lighting, instrumentation, communications, fire &
gas, ESSI, pre-commissioning, check-out, and start-up of 4,500 ton production
platform facility.
Type of Contract: Lump
Sum
Contract Period:
October 1997 - March 1998
Contract Manhours:
32,300
Contract Value:
$1,253,000 |
|
Owner: Anadarko
Petroleum Corporation
Contract Holder: Gulf
Marine Fabricators
Scope of Work: Anadarko
Tanzanite Production Deck
Complete power,
electrical, controls, lighting, instrumentation, communications, fire &
gas, ESSI, pre-commissioning, check-out, and start-up of 4,000 ton production
platform facility.
Type of Contract: Lump
Sum
Contract Period: April
2000 - July 2000
Contract Manhours:
28,000
Contract Value:
$1,250,000 |
|
Owner: Duke Energy -
Trunkline Gas Co.
Contract Holder: Brown
& Root Energy Services
Scope of Work: Anadarko
Tanzanite Production Deck
Complete power,
electrical, controls, lighting, instrumentation, communications, fire &
gas, ESSI, pre-commissioning, check-out, and start-up of 2,500 ton production
platform facility.
Type of Contract: Lump
Sum
Contract Period:
November 1997 - February 1998
Contract Manhours:
26,400
Contract Value:
$1,123,000 |
|
Owner: Amerada Hess
Corporation
Contract Holder:
Amerada Hess Corporation
Scope of Work: Bald
Pate Project - Garden Banks - Offshore Hook-Up
Complete power,
control and instrument cable tray and cable installation. Complete
interconnects all systems - power, fire & gas, instrumentation,
communications, etc. Pre commissioning and start-up for offshore hook-up.
Type of Contract: Time
& Material
Contract Period: March
1998 - April 1998
Contract Manhours:
9,873
Contract Value:
$981,687 |
|
Owner: Transocean
Contract Holder: Gulf
Marine Fabricators
Scope of Work: Deep
Seas Discovery Integrated Work
Complete electrical
and instrumentation hook-up on the 2nd of two (2) drilling ships.
Type of Contract: Lump
Sum
Contract Period: March
2000 - May 2000
Contract Manhours:
27,500
Contract Value:
$934,000 |
|
Owner: Texaco
Exploration, Inc.
Contract Holder: J. Ray
McDermott, Inc.
Scope of Work: Texaco
Osprey Oil Production Facility
Furnish, install,
test, pre-commission and start up of all power, control, instrumentation, fire
& gas communications and navigation aids for 1,600 ton oil & gas
production facility.
Type of Contract: Lump
Sum
Contract Period:
October 1998 - January 1999
Contract Manhours:
13,400
Contract Value:
$589,641 |
|
Owner: PEMEX
Contract Holder: Powell
Industries Offshore Division
Scope of Work: PEMEX
Platform PB-AB-1 Control Room Building
Electrical
installation for MCC Control Building for PEMEX PB-AB-1 Platform
Type of Contract: Lump
Sum
Contract Period:
February 2000 - April 2000
Contract Manhours:
2,300
Contract Value:
$369,839 |
|
Owner: Duke Energy -
Trunkline Gas Co.
Contract Holder: Duke
Energy - Trunkline Gas Co.
Scope of Work: Tri-Mars
Deck Outfitting - Ship Shoal 139 Block - Offshore Hook-Up
Complete power,
control & instrument cable tray and cable installation. Complete
interconnects all systems - power, fire & gas, instrumentation,
communications, etc. Pre-commissioning and
start up.
Type of Contract: Time
& Material
Contract Period: April
1998 - June 1998
Contract Manhours:
8,300
Contract Value:
$325,000 |
|
Owner: PEMEX
Contract Holder: Powell
Industries Offshore Division
Scope of Work: PEMEX
Platform PB-AB-1 Switchgear and Control Room Building
Electrical
installation for PEMEX Platform PB-AB-1 Switchgear and Control Building
Type of Contract: Lump
Sum
Contract Period:
December 1999 - January 2000
Contract Manhours:
1,860
Contract Value:
$270,000 |
|
Owner: Transmontaigne
Terminaling, Inc.
Contract Holder:
Dolphin Services
Scope of Work: Baton
Rouge Barge Terminal/West Feliciana Barge Terminal
Complete electrical
& instrumentation hook-up of Modularized Barge Fueling Terminal.
Type of Contract: Lump
Sum
Contract Period:
October 1999 - December 1999
Contract Manhours:
4,900
Contract Value:
$197,673 |
|
Owner: Anadarko
Petroleum Corporation
Contract Holder: Powell
Industries Offshore Division
Scope of Work: Anadarko
Tanzanite Production Deck
Complete power,
electrical, controls, lighting, instrumentation, communications, fire &
gas, ESSI, pre-commissioning, check-out and start-up of a 4,000 ton production
deck.
Type of Contract: Lump
Sum
Contract Period:
November 1999 - December 1999
Contract Manhours:
Contract Value:
$149,985 |
|
Owner: Anadarko
Petroleum Corporation
Contract Holder: Powell
Industries Offshore Division
Scope of Work: Anadarko
Hickory MCC Control Building Project
Electrical
installation for MCC Control Building for Anadarko Hickory Production Platform.
Type of Contract: Lump
Sum
Contract Period:
December 1999 -
Contract Manhours:
2,200
Contract Value:
$133,353 |
|
Owner: City of
Lafeyette
Contract Holder: Cajun
Contractors, Inc.
Scope of Work:
Demineralization Regeneration Water Retention Tank
Install, test and
start-up process controls, PLC neutralization panel, power and controls for
dual tank ph equalization system.
Type of Contract: Lump
Sum
Contract Period: August
1998 - November 1998
Contract Manhours:
4,300
Contract Value:
$124,000 |
|
Owner: AKZO Nobel
Chemical
Contract Holder: Jacobs
Constructors
Scope of Work: AKZO
Nobel ACINA Technical Support
Headed up completion
work (oversee) instrument contract, which was being performed by another
contractor on a time & material basis.
Type of Contract: Time
& Material
Contract Period: March
17, 2000 - June 2, 2000
Contract Manhours:
2,122
Contract Value:
$115,000 |
|
Owner: Shell Deepwater
Development, Inc.
Contract Holder: Gulf
Marine Fabricators
Scope of Work: Shell
Brutus Helideck and Flareboom
Electrical and
instrumentation installation on the Shell Brutus Helideck and Flareboom.
Type of Contract: Lump
Sum
Contract Period:
February 2001 - March 2001
Contract Manhours:
2,000
Contract Value: $99,940
|
|
Owner: Mobil Producing
U.S.A.
Contract Holder:
Mustang Engineering, Inc.
Scope of Work: Mobil
Jade Living Quarters
Electrical
installation and hook-up for the Mobil Jade Living Quarters Project.
Type of Contract: Lump
Sum
Contract Period: June
1999 -
Contract Manhours: 912
Contract Value: $69,420
|
|
Owner: GSF Energy, LLC
Contract Holder: Shaw
Constructors, Inc.
Scope of Work: Fresh
Kill Landfill Gas Facility Module Fabrication Outfit
Type of Contract: Lump
Sum
Contract Period: March
2001 - April 2001
Contract Manhours:
1,500
Contract Value: $54,904
|
|
Owner: Shaw Group, Inc.
Contract Holder:
Sunland Fabricators, Inc.
Scope of Work: Stress
Furnace Control Room Electrical
Underground feeder
from fabrication building to new control room, installation of lighting,
receptacles in control room, installation of a 75Kva transformer, 480V - 3
phase 400 amp distribution panel, and installation of 400 amp switchgear.
Type of Contract: Lump
Sum
Contract Period: 2.5
weeks - March 1999
Contract Manhours: 926
Contract Value: $19,736
|
|
Owner: Shaw Group, Inc.
Contract Holder:
Sunland Fabricators, Inc.
Scope of Work:
Electrical / Fiber Optics
Trenching from front
office to fabrication building, then splitting off in fabrication building and
running fiber optics to end users at opposite sides of building.
Type of Contract:
Contract Period: 2.3
weeks - March 1999
Contract Manhours: 812
Contract Value: $15,761
|
|